[I-49]Report of replacement of vertical members in steel truss bridge
〇Hiroaki Kawamura1, Tsutomu Ueyama1, Takuya Suzuki1, Masanao Hayashi2, Shingo Hisano2, Kenjirou Kootsuka2(1.Japan Bridge, 2.West Nippon Expressway)
Keywords:
Steel Truss Bridge,Replacement of Vertical Members,Corrosion,Repair of Bridges
Corrosion progressed in the vertical members, and it became necessary to replace them with new members. In order to replace the vertical member, it is necessary to temporarily remove the vertical member. Ensure structural stability during construction. Know the axial force of action in advance. The generated stress equivalent to that of the existing member is re-transferred to the new member. These were the problems. By this method, we were able to work in a state where stability was ensured. By measuring the strain, it was confirmed that the same load as before the replacement was re-transferred to the replaced member.