[1B_PL04]Panel DiscussionChallenges for Decommissioning of Fukushima Daiichi Nuclear Power Station - Overall Process and Solid Radioactive Waste Management -
*Naoki Kondo1, *Kazuyuki Kato2, *Yoshikazu Koma3, *Tamotsu Kozak4, *Osamu Tochiyama5, *Naoki Shichida6 (1. MRI, 2. NDF, 3. JAEA, 4. Hokkaido Univ., 5. NSRA, 6. TEPCO HD)
In the decommissioning work of the Fukushima Daiichi Nuclear Power Station (1F), the storage, treatment, and disposal for the radioactive waste become more important with the progress of decommissioning. In this session, it introduces that the current status and future of radioactive waste on 1F decommissioning and R&D activities on 1F decommissioning in the project of decommissioning and contaminated water management, which has been carried out by support of the Ministry of Economy, Trade and Industry. In order to understand the issues related to radioactive waste management and to consider the approaches from the back-end of nuclear fuel cycle to promote the 1F decommissioning, this panel session discusses issues that should be addressed and studied in advance with focus on the completion of the decommissioning.