Presentation Information
[VI-666]Planning of a temporary ramp under low head clearance and narrow site conditions by using temporary construction girder and jacking-up of the existing elevated railway
*Toru Yabuki1, Takuya Matsumoto1, Hibi Ryosuke1, Kitade Keiichiro1, Murakami Kenji1, Ishiwata Kouichi2, Okita Motoshi2 (1. OBAYASHI CORPORATION, 2. Keikyu Corporation)
Keywords:
low head clearance,narrow site,temporary construction girder,jacking-up