[V-355]Experiment on topping concrete using setting time adjustment additive for shortening of finishing works

*Chiho Terada1, Ayumi Yanagisawa1, Kazuhiro Aizawa1, Takayuki Higuchi1, Shinji Urano2, Gomita Hisato2, miyata Yoshikazu2 (1. Denka Company Limited, 2. SHIMIZU CORPORATION)

[V-356]Finishing Work Time of Concrete with Setting Accelerating Admixture Applied to Hydroelectric Power Plant Repair Work

*Shinji Urano1, Yoshikazu Miyata1, Hisato Gomita1, Kazuhiro Aizawa2 (1. Shimizu Corporation, 2. Denka Company Limited)

[V-357]Estimation of demolding time by measuring concrete temperature using thermolabels

*Kazumasa Morihama1, Takehiro Sawamoto1, Toru Shinozaki1 (1. Institute of Technologists)

[V-358]Study on the causes of concentrated peeling on the concrete lining side wall during winter construction

*Liang Jun1 (1. taisei advanced center of technology)

[V-359]Analytical Study on the Effect of Heat Storage in Steel Formwork on the Surface Quality of Boundary Concrete

*Hiroto Kojima1, Kozu Mineki2, Chunhe LI1 (1. University of Miyazaki, 2. NIPPON SHARYO, LTD.)

[V-360]Effect of Curing with Insulated and Wet Curing Sheet on Strength and Durability

*Takashi Kawanishi1 (1. OBAYASHI CORPORATION)

[V-361]Effects of steam curing during hot summer season on the strength development of concrete

*Kazuki Aota1, Hisashi Saito2, Shinichiro Hashimoto1, Yuki Ono1, Katsunobu Shinkai2 (1. Chiba Institute of Technology, 2. Sumitomo Osaka Cement Co.,Ltd.)

[V-362]production of bentonite-mixed soil by linking s+4 construction method control equipment to stationary plant equipment.

*taiga Shiota1, Yasunori Arai1, Yuuzi Inamoto2, Takahisa Saitou2, Hiroyasu Sekiya2, Tutomu Saitou3, Yuuki Sakoda4, Shinsuke Ujiie4 (1. seibu construction company, 2. leaf air company, 3. skmaterial company, 4. houjun company)