Session Details

各種基礎(2)

Thu. Sep 11, 2025 11:10 AM - 12:30 PM JST
Thu. Sep 11, 2025 2:10 AM - 3:30 AM UTC
231

[VI-643]New approach for improvement of BCH (Bottom CirculationHole) construction method~Field application example of improved drilling bits~

*Takumi Abe1, Muneyuki Ogawa1, Yoshinori Hattori2, Takuya Higashida3, Tajima Shinichi3, Ide yusuke3 (1. Chemical Grouting Co.,Ltd, 2. Keikyu Corporation, 3. KAJIMA CORPORATION)

[VI-644]Operation check of construction machinery for Shinso-MaN(W) construction method

*Hikari Ogawa1, Yamamoto Atsushi, Nakmura Seisi1, Minato Kenji1, Takeda Shigetsugu2, Aoki Yoshinori3 (1. Tekken Corporation, 2. J-TEC CORPORATION, 3. Tohoku Electric Power Network Co., Inc.)

[VI-645]Proposal for Foundation Design Adaptation in Response to the Upsizing of Onshore Wind Turbines

*Hitoshi Imai1, Soichiro Yoshida1 (1. TODA CORPORATION)

[VI-646]Selection of pile foundation for widening retaining wall in narrow area

*Noritsugu Kajita2, Daisuke Kobayashi1, Keisuke Masuda1, Takumi Ishida1, Kazuhiro Hattori3, Shunsuke Kitagawa3 (1. Central Nippon Expressway Company Limited, 2. Shimizu-Toa JV, 3. SHIMIZU CORPORATION)

[VI-647]Study on construction method and construction of long steel pipe sheet piles on reclaimed land

*Kanata Takahiro1, Aramaki Yuya2, Iyoki Tatsuya2, Kadowaki Shinji1 (1. TAISEI CORPORATION, 2. Hanshin Expressway Company Limited)

[VI-648]Application of lightweight soil mixed with air bubbles (FCB) for embankment of National Highway 16 bypass disaster restoration work

*Takahiro Hino1, Kazutosi Yanase1 (1. TAISEI CORPORATION)