[3B09]Unique Integrated Testing Facility (UNITY-1) Project(2) Commissioning and Safe Operation of Unique Integrated Testing Facility(UNITY-1)

*Takashi Ino1, Minoru Jimma1, Kyousuke Namba1, Satoshi Ogawa1, Yoshifumi Kume1, Colin Bause1, Satoshi Konishi1, Naoko Ahikawa1 (1. Kyotofusioneering.ltd)

Keywords:

LiPb,Commissioning,Safety

Kyoto Fusioneering has constructed and commissioned a LiPb loop (UNITY-1), which operates at 500°C with a 300 L LiPb inventory and is accompanied by two electromagnetic pumps, dump tanks, electric heaters etc. Performance tests using protium and deuterium dissolved in LiPb by a tritium fuel extraction system and high-temperature blanket tests are planned for the future. This section reports on the status of the first phase of UNITY-1, process engineering, commissioning, safety considerations and issues from a safety review perspective.