[Data_Collection-23]E-NEXCO INDIA's Initiatives for Pavement Condition Survey in India
*Kentaro Oba1, Tatsuo Takano1, Kazuhiko Kumada2, Michiya Kitayama3, Kazuhiro Okajima1, Keizo Endo4, Takehiro Yamamoto1 (1. East Nippon Expressway Company Limited (Japan), 2. Nippon Expressway Research Institute Company Limited (Japan), 3. E-NEXCO INDIA PRIVATE LIMITED (India), 4. Nexco-East Engineering Company Limited (Japan))
Keywords:
Pavement Condition Survey,Pavement Maintenance,Indian Expressway,International Deployment of Japanese Technology,Measurement under Severe Conditions
East Nippon Expressway Company Limited (NEXCO East) has long promoted international contributions based on technologies and expertise developed through the expressway construction and maintenance in Japan. E-NEXCO INDIA, established in 2019 as the first international subsidiary of the NEXCO East Group, has customized NEXCO East's pavement condition survey technology to meet Indian specifications. E-NEXCO INDIA is currently conducting the pavement condition survey approximately 14,000 km of lanes per year on Indian expressways.
The primary challenges for the survey were compliance with legal regulations associated with technology transfer and adaptation to India's severe survey conditions. For survey vehicle fabrication, all vehicles operating within India were required to comply with the Central Motor Vehicle Rules (CMVR) stipulated by the Ministry of Road Transport and Highways.
However, in Japan and India, Japanese automobile manufacturers did not produce trucks that met CMVR requirements, making it practically impossible to build a survey vehicle using a Japanese truck. To overcome this, a cargo box with measurement equipment was manufactured in Japan, shipped to India and mounted onto an Indian truck procured locally in order to build the survey vehicle.
The pavement condition survey in India faced severe conditions such as high temperatures and pervasive fine dust, causing equipment malfunctions not experienced in Japan. Furthermore, India's vast geography posed additional challenges. The farthest survey section was approximately 2,800 km from the vehicle base, and numerous unpaved sections along transportation routes resulted in shocks and vibrations that damaged the vehicle and measurement equipment.
Through close collaboration with the Japanese manufacturer of the survey system, the NEXCO East Group systematically solved these challenges and established a stable operational framework for the survey.
This paper reports on the knowledge gained, technical solutions implemented, and future initiatives based on four years of experience in pavement condition surveys in India.
The primary challenges for the survey were compliance with legal regulations associated with technology transfer and adaptation to India's severe survey conditions. For survey vehicle fabrication, all vehicles operating within India were required to comply with the Central Motor Vehicle Rules (CMVR) stipulated by the Ministry of Road Transport and Highways.
However, in Japan and India, Japanese automobile manufacturers did not produce trucks that met CMVR requirements, making it practically impossible to build a survey vehicle using a Japanese truck. To overcome this, a cargo box with measurement equipment was manufactured in Japan, shipped to India and mounted onto an Indian truck procured locally in order to build the survey vehicle.
The pavement condition survey in India faced severe conditions such as high temperatures and pervasive fine dust, causing equipment malfunctions not experienced in Japan. Furthermore, India's vast geography posed additional challenges. The farthest survey section was approximately 2,800 km from the vehicle base, and numerous unpaved sections along transportation routes resulted in shocks and vibrations that damaged the vehicle and measurement equipment.
Through close collaboration with the Japanese manufacturer of the survey system, the NEXCO East Group systematically solved these challenges and established a stable operational framework for the survey.
This paper reports on the knowledge gained, technical solutions implemented, and future initiatives based on four years of experience in pavement condition surveys in India.