Session Details
[1C01-05]Refinery maintenance(1)
Thu. Oct 29, 2026 10:10 AM - 11:30 AM JST
Thu. Oct 29, 2026 1:10 AM - 2:30 AM UTC
Thu. Oct 29, 2026 1:10 AM - 2:30 AM UTC
Room-C (2F-International Conference Room)
Chair:
Toshikazu Ohmura (ENEOS)
Toshikazu Ohmura (ENEOS)
[lUQgwKhS-1add]Process Eqipment Div. chief remarks
[1C01]Tightening training system of bolted flange connection for the worker established by JAMSEC (Japan Association of Maintenance and Service Contractors) (part 2)
○KOJI KONDO1 (1. RAIZNEXT Corporation)
[1C02]A case study of initiatives toward zero leakage from flanged joints
○Nobuyasu Takahama1 (1. Engineering&Maintenance Section Aichi Complex Idemitsu Kosan Co.,Ltd.)
[1C03]Maintenance considerations for heavy oil pumps
○Yuta Araki1 (1. SHOWA YOKKAICHI SEKIYU CO., LTD.)
[1C04]Response to piping construction in sulfide stress cracking environment— Examination of construction area selection through mock-up testing —
○mamoru tsurushima1, masao hirano2 (1. Idemitsu Kosan Co., Ltd. Chiba Complex Inspection & Reliability Section, 2. Idemitsu Kosan Co., Ltd. Chiba Complex Engineering & Maintenance Section)
[1C05]Examples of replacing float-type level gauges with radar-type level gauges due to malfunctions.
○WATARU HATASAWA1 (1. Fuji Oil Company)